TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: DIRECTOR OF PUBLIC WORKS DATE: October 1, 2002 SUBJECT: Notice of Completion for TRAIL REPAIRS, AND FENCING CONSTRUCTION AT INSPIRATION POINT AND SHORELINE PARK STAFF COORDINATOR: Bindu Vaish, Engineering Technician RECOMMENDATIONS
BACKGROUND On June 12, 2002, City Council awarded a contract to Ryco Construction for Trail repairs and fencing construction at Inspiration Point and Shoreline Park. Pursuant to the approved contract, the work was completed at the following cost:
To improve the safety of the hikers on Inspiration point the fence was revised resulting in an additional change order totaling $3,730. CONCLUSION Ryco Construction has completed all work in accordance with the contract documents. Therefore, the work should be accepted as a complete and the Notice of completion filed with the County Recorder. FISCAL IMPACT The recommended action will have no fiscal impact. Respectfully submitted, ________________________________ Reviewed, ___________________________ Attachments: |