| Back To Agenda | Print Page | ||
|
|
|||
|
TO: HONORABLE MAYOR AND MEMBERS OF CITY COUNCIL FROM: DIRECTOR OF PUBLIC WORKS DATE: JUNE 17, 2003 SUBJECT: NOTICE OF COMPLETION – VALLON DRIVE TRAFFIC SIGNAL INSTALLATION PROJECT Staff Coordinator: Nicole Jules, Sr. Engineer RECOMMENDATIONS:
BACKGROUND & ANALYSIS On September 3, 2002, City Council awarded a contract to Steiny & Company, Inc. for the construction of the Vallon Drive Traffic Signal Project. Pursuant to the approved contract, the work has been satisfactorily completed at the following cost:
Change Orders for this project comprised 19% of total construction cost. Change orders included construction of an Edison hand-hole for electrical service, construction of a special concrete spread footing to avoid unforeseen buried utility, rental of a changeable message board for added safety during the initial signal turn-on period and replacement of a private concrete driveway. FISCAL IMPACT The recommended action will have no fiscal impact. CONCLUSION Steiny & Company, Inc. has successfully completed all work in accordance with the plans and specifications for this project. Therefore, the work should be accepted as complete and a Notice of Completion filed. Respectfully Submitted,
___________________________ Reviewed, _________________________ Attachments: Notice of Completion |