TO: HONORABLE MAYOR AND COUNCILMEMBERS
FROM: DIRECTOR OF PLANNING, BUILDING & CODE ENFORCEMENT
DATE: JUNE 7, 2005
SUBJECT: AMENDMENT NO. 2 FOR CONTRACT TO PREPARE THE ENVIRONMENTAL IMPACT REPORT FOR THE POINT VIEW PROJECT (6001 PALOS VERDES DRIVE SOUTH)
Staff Coordinator: Kit Fox, AICP, Senior Planner
RECOMMENDATION
Authorize the Mayor and the City Clerk to sign an amendment to the professional services agreement with PCR Services Corporation (PCR) in an amount not to exceed $63,434 to complete the preparation of an Environmental Impact Report (EIR) for the Point View project, located at 6001 Palos Verdes Drive South.
BACKGROUND
On July 15, 2003, the City Council approved a contract with PCR in the amount of $200,384 for the preparation of the Point View EIR. A contract amendment in the amount of $38,980 was approved by the City Council on October 5, 2004. The Draft EIR is currently nearing completion. However, due the high level of complexity of the project and other unanticipated factors, additional work beyond the original scope of the contract has been conducted or will be necessary to complete the EIR. Therefore, PCR has requested an amendment to the contract to cover this additional "out of scope" work.
DISCUSSION
The attached letter from PCR describes the "out of scope" work covered by the proposed contract amendment. This work relates to the preparation and review of the Screencheck Draft EIR. Staff, PCR and the project proponent agree that all of these services are necessary to complete the EIR. Therefore, the total contract amendment requested by PCR is $63,434.
With respect to the status of the Draft EIR itself, PCR has prepared the first full Screencheck Draft EIR for the review of Staff and the project proponent. Staff, PCR and the project proponent are working to complete the review of the Screencheck Draft EIR —including the items covered by this contract amendment—for public release and comment later this month.
CONCLUSION
For the reasons noted above, Staff recommends that the City Council authorize the Mayor and the City Clerk to sign an amendment to the professional services agreement with PCR in an amount not to exceed $63,434 to complete the preparation of the EIR for the Point View project.
ADDITIONAL INFORMATION
The project applicant and PCR have been advised of the City Council’s consideration of this matter. In addition, Staff has notified a number of other parties who have previously expressed interested in this project.
FISCAL IMPACT
The amendment Point View EIR contract has no fiscal impact on the City since the cost of preparation for the EIR is borne by the project applicant, York Long Point Associates.
Respectfully submitted:
Joel Rojas, AICP, Director of Planning, Building and Code Enforcement
Reviewed by:
Les Evans, City Manager
Attachments:
Amendment Request No. 2, Point View EIR