TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: DIRECTOR OF PUBLIC WORKS
DATE: SEPTEMBER 20, 2005
SUBJECT: NOTICE OF COMPLETION FOR THE MIRA VISTA SPEED HUMP PROJECT
RECOMMENDATION
BACKGROUND & ANALYSIS
The project consisted of the installation of twelve, three inch tall, 12 feet wide speed humps spanning the traveled way from gutter to gutter, painting chevron striping on the humps and the installation of signage in the project area. The contract for the project was awarded to Sully-Miller Construction Company on June 21, 2005. Since that time all work has been satisfactorily completed.
The final project costs are as follows:
| Contract Award Amount |
$45,380 |
| Authorized Contingency Budget |
$10,000 |
| Authorized Total Construction Budget |
$55,380 |
| Net Change Orders |
$ 3,792.36 |
| Total Construction Costs |
$49,172.36 |
The total construction cost is greater than the award amount but less than the total authorized budget. One change was made to the contract which changed the number of signs installed and modified the locations they were to be installed.
FISCAL IMPACT
The recommended action will have no fiscal impact. This project was budgeted in the Traffic Management Program fund.
CONCLUSION
Sully-Miller Construction Company has successfully completed all work in accordance with the plans and specifications. Therefore, the work should be accepted as complete and a Notice of Completion filed.
Respectfully submitted:
Dean E. Allison
Director of Public Works
Reviewed
Les Evans
City Manager