RECOMMENDATION

Review and reconfirm by a four/fifths (4/5) vote, the Council’s previous action on December 21, 2004 to authorize staff to conduct an informal bid process to repair the Tarapaca Storm Drain.

BACKGROUND

On December 21, 2004, the City Council found that an emergency exists concerning the repair of the Tarapaca Storm Drain. This emergency situation will not permit a delay resulting from a competitive solicitation for bids to line the existing pipe.

DISCUSSION

Approval of both the informal bid process, the pre-ordering of the pipe and the negotiation and execution of the construction contract with the City’s on-call Roadway Maintenance Contractor, Hardy & Harper Inc., and the expenditure of the $95,000 for this work required a four-fifths (4/5) vote of the Council under Public Contract Code Section 22050(a)(1).

In addition, Public Contract Code Section 22050(c)(1) requires that when a governing body takes action under Section 22050(a)(1), it must review that action and reaffirm it by a four-fifths vote at each subsequent regularly scheduled meeting until the action is terminated. Accordingly, because the repair has not yet been completed, staff has placed this item on tonight’s agenda. This item will be placed on each subsequent agenda until the project is completed.

CURRENT STATUS

The Contractor is continuing his work on the hillside behind the homes on Tarapaca Drive. The hand excavation of slope anchors is complete concrete has been placed to anchor the pipe and pipe installation is largely complete. Work is underway to revise the design of the outlet structure and complete the remaining work as presented in the following schedule.

 

Week Activity
December 12 Redesign of the Outlet structure to be completed this week.
December 19 Installation of the storm drainpipe associated with the Outlet structure is to be completed this week.
December 26 Construction of the Outlet Structure is to be completed this week.

Respectfully submitted:

Ray Holland
Interim Director of Public Works

Reviewed

Les Evans
City Manager

Attachment: A) Statement of Estimated General Fund Reserves
B) Status of Storm Drain Funding