Rancho Palos Verdes City Council
   

APRIL 4, 2006 PONTEVEDRA EMERGENCY STORM DRAIN REPAIRS APRIL 4, 2006 PONTEVEDRA EMERGENCY STORM DRAIN REPAIRS
APRIL 4, 2006 PONTEVEDRA EMERGENCY STORM DRAIN REPAIRS



TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

FROM: DIRECTOR OF PUBLIC WORKS

DATE: APRIL 4, 2006

SUBJECT: PONTEVEDRA EMERGENCY STORM DRAIN REPAIRS


RECOMMENDATION

Review and reconfirm by a four/fifths (4/5) vote, the Council’s previous action on December 6, 2005 to authorize staff to conduct an informal bid process to repair the Pontevedra storm drain line.

BACKGROUND

On December 6, 2005, the City Council found that an emergency exists concerning the repair of the Pontevedra Storm Drain line. This emergency situation will not permit a delay resulting from a competitive solicitation for bids to line the existing pipe.

DISCUSSION

Approvals of the informal bid process, the pre-ordering of materials, the negotiation and execution of the $100,000 construction contract with Peterson-Chase, General Engineering Construction, Inc., and the $20,000 professional services agreement with PSOMAS required a four-fifths (4/5) vote of the Council under Public Contract Code Section 22050(a)(1).

In addition, Public Contract Code Section 22050(c)(1) requires that when a governing body takes action under Section 22050(a)(1), it must review that action and reaffirm it by a four-fifths vote at each subsequent regularly scheduled meeting until the action is terminated. Accordingly, because the requirements of the contract have not yet been completed, staff has placed this item on tonight’s agenda. This item will be placed on each subsequent agenda until all aspects of the contract are completed.

CURRENT STATUS

Contracts were executed with Peterson-Chase (construction Contractor) and PSOMAS (project Inspector) in December 2005. All construction work associated with repairing the storm drain line on Pontevedra Dr., from the manhole adjacent to 28408 Pontevedra Dr. on the west extending easterly within an easement and terminating within the State Right of Way on Western Ave, has been completed.

Staff is awaiting receipt of the final construction related costs. Upon review and approval of acceptable costs staff will recommend acceptance of the work.

Respectfully submitted:


____________________
Ray Holland
Interim Director of Public Works

Reviewed

____________________________
Les Evans
City Manager

Attachment: A) Status of Storm Drain Funding

--------